M.Erdmann Jan 15, 2000
Status: Complete
The Project Plan is simple (status):
The table below shows the current status of the project and the personal assignments to theses jobs.
Issue |
Activity |
Status |
assignment |
Specification |
complete |
M.E | |
Specification |
review |
M.E | |
Specification |
complete |
M.E | |
Functionality (Phase 2) |
Specification |
open |
M.E |
Specification |
end of Jan. |
M.E | |
Specification |
review |
||
Specification |
complete |
||
coding |
|||
Implementation |
|||
Test |
|||
Specification |
end of Nov. |
||
Implementation |
end of Dec. |
||
Test |
end of Dec. |
||
Specification |
|||
Implementation |
|||
Test |
|||